Pasadena to Azusa Construction Update; Azusa to Montclair Kicks Off
Significant progress continues along the 11.5-mile corridor, as the Pasadena to Azusa project nears 50% completion. Most bridge structures and at-grade crossings have been completed or are nearing completion, and light rail track will soon be laid along the corridor. Work is underway at four of the six stations, and in mid-November the third (and final) concrete pour for the Duarte Station platforms took place. The Operations Campus is also moving along on schedule. Light rail track is being installed, and nearly all of the OCS (overhead catenary system) pole foundations for the future system to power the trains are now ready. Below are some highlights of recent construction:
Operations Campus Highlights: |
|
The car cleaning platform is now poured and the forms removed. |
Track ties and rails are set on several storage tracks, and initial and flood ballast is being placed. |
Arcadia Highlight: | Monrovia Highlight: |
Santa Anita Ave Bridge abutments supports are complete and ready for the girders to be set in early 2014.
|
The Santa Anita Wash bridge was completed in October. Here, girders are being set.
|
Duarte Highlight: | Irwindale Highlight: |
Here, the first of three completed concrete pours for the Duarte station platforms.
|
The 700-ft San Gabriel River Bridge structure was completed in time for the start of the official rainy season; an Army Corp of Engineers requirement.
|
Downtown Azusa Highlight: | Azusa-Citrus Highlight: |
Track panels are being installed across San Gabriel Ave, one of only two unfinished at-grade crossings to be completed in the city of Azusa.
|
Concrete girders were set onto the light rail bridge abutments in November, completing the two Citrus Ave light rail bridge structures.
|
Azusa to Montclair Update:
Following environmental clearance earlier this year when a locally preferred alternative was selected, the Construction Authority has now officially kicked off the next phase of work for the Foothill Extension from Azusa to Montclair! Over the next two years, we will work to advance the project's design/engineering to a point where it will be ready for a design-build procurement. We will also re-engage the previously selected station artists, so they can oversee the material and color choices for their station, as well as advance the artwork design. Here are highlights from recent kick-off meetings:
Photo from October 23, 2013 Azusa to Montclair Segment Kick-Off Meeting where city staff and officials were brought together to discuss the upcoming effort to advance the project design. They were provided information on what they could expect over the next two years of work.
|
|
|
On November 20, a pre-proposal conference was held at the Arcadia City Hall for interested consultants to learn about how they can get involved in advancing the design for the 12.3-mile project. More than 80 representatives from more than 70 local consulting firms were in attendance to listen and ask questions about the procurement process, scope of work and timetable. The Construction Authority intends to issue the Request for Proposals in early January 2014.
Have you checked your map lately? Learn the latest about construction in your community!
Other Easy Ways to Stay Updated:
Community Resources Available:
Arcadia
400 N. Santa Anita Ave, Suite 101-B, Arcadia, CA 91006
(Northeast corner of Santa Anita Ave and La Porte St)
Hours: Mondays and Wednesdays ONLY: 8 a.m. - 4 p.m.
Monrovia
406 E. Huntington Dr, Suite 202, Monrovia, CA 91016
(Construction Authority Offices)
Hours: Mondays through Friday: 8 a.m. - 5 p.m.
Azusa
1300 W. Optical Dr, Suite 500, Azusa, CA 91702
Hours: Mondays through Friday: 8 a.m. - 5 p.m.
|
|
No comments:
Post a Comment