Monday, March 3, 2014

Series of Foothill Blvd Closures at Railroad Bridges in Azusa Starts Friday
 
WHEN - Friday, March 7, 2014 to late-May 2014
 
Over the next few months, crews will be installing steel beams to complete the three rail bridge structures (one for freight and two for light rail) over Foothill Blvd. This work will require a full weekend closure and long-term, off-peak one-way closures of Foothill Blvd, between Vernon Ave and Orange Ave.
 
On Friday, March 7 at 9 PM, Foothill Blvd will be closed to thru-traffic in both directions between Vernon Ave and Orange Ave until Monday, March 10 at 4 AM.
 
Then, beginning Monday, March 10, eastbound Foothill Blvd, between Vernon Ave and Orange Ave, will be closed to thru-traffic daily for six weeks between the hours of 4 AM and 2 PM only.
 
Once the eastbound work is completed, beginning approximately on Monday, April 21, westbound Foothill Blvd, between Vernon Ave and Orange Ave, will be closed to thru-traffic daily for six more weeks between the hours of 9 AM and 10 PM only.
 
Detours and signage will be in place to guide motorists around the construction activity. The sidewalk will remain closed to pedestrians during the full weekend closure, but pedestrian access will be available on one side of Foothill Blvd during the one-way closures.
 
Local businesses, and access to them, on Foothill Blvd will remain open during the closures. We encourage you to take the time to help these businesses during these closures.

 
For more information or to view other current construction notices, click here.